Causal Loop Analysis on the Impact of Schedule Risks in Prefabrication Housing Production in Hong Kong

  • Conference paper
  • First Online:
Proceedings of the 21st International Symposium on Advancement of Construction Management and Real Estate

Abstract

Every country is dealing with its own housing problems; however, none compares with Hong Kong where housing has always been a major concern as a result of low supply over the past decades. Against the constraints in delivering sufficient houses, prefabrication as a solution has been increasingly advocated for its potential benefits of rapid process and better quality. However, schedule delay caused by various risks affected the prefabrication housing production (PHP) in Hong Kong, which can be further exacerbated by the fact that the whole prefabrication manufacturing sector has moved to offshore areas in the Pearl River Delta region. This study applies system dynamics (SD) to recognize and investigate the potential effects of various risks on the scheduling of PHP. A causal-loop diagram is then constructed to analyze the impact of schedule risks in PHP based on the identified variables in the defined system. This study is of value in exploring interactional and interdependent relationships underlying the identified schedule risks within the three sub-systems including schedule risk sub-system, prefabrication housing production sub-system and schedule performance sub-system.

This is a preview of subscription content, log in via an institution to check access.

Access this chapter

Institutional subscriptions

References

  • Ansari N, Seifi A (2013) A system dynamics model for analyzing energy consumption and CO2 emission in Iranian cement industry under various production and export scenarios. Energy Policy 58:75–89

    Article  Google Scholar 

  • Aye L, Ngo T, Crawford R, Gammampila R, Mendis P (2012) Life cycle greenhouse gas emissions and energy analysis of prefabricated reusable building modules. Energy Build 47:159–168

    Article  Google Scholar 

  • Eastman CM, Sacks R (2008) Relative productivity in the AEC industries in the United States for on-site and off-site activities. J Constr Eng Manage 134:517–526

    Article  Google Scholar 

  • Ergen E, Akinci B (2008) Formalization of the flow of component-related information in precast concrete supply chains. J Constr Eng Manage 134:112–121

    Article  Google Scholar 

  • Fan CY, Fan PS, Chang PC (2010) A system dynamics modeling approach for a military weapon maintenance supply system. Int J Prod Econ 128:457–469

    Article  Google Scholar 

  • Ford A (1996) Testing the snake river explorer. Syst Dyn Rev 12:305–329

    Article  Google Scholar 

  • Gibb AG (1999) Off-site fabrication: prefabrication, pre-assembly and modularisation. Wiley, New York

    Google Scholar 

  • Hong J, Shen GQ, Mao C, Li Z, Li K (2016) Life-cycle energy analysis of prefabricated building components: an input–output-based hybrid model. J Clean Prod 112:2198–2207

    Article  Google Scholar 

  • Hong Kong Census and Statistics Department (HKCSD) (2015) The Hong Kong annual digest of statistics 2015, http://www.censtatd.gov.hk/hkstat/sub/sp140.jsp

  • Hong Kong Housing Authority (HKHA) (2016) Number of applications and average waiting time for public rental housing

    Google Scholar 

  • Ingrao C, Lo Giudice A, Mbohwa C, Clasadonte MT (2014) Life cycle inventory analysis of a precast reinforced concrete shed for goods storage. J Clean Prod 79:152–167

    Article  Google Scholar 

  • Jaillon L, Poon CS (2009) The evolution of prefabricated residential building systems in Hong Kong: a review of the public and the private sector. Autom Constr 18:239–248

    Article  Google Scholar 

  • Jeong JG, Hastak M, Syal M (2009) Framework of manufacturer-retailer relationship in the manufactured housing construction. Constr Innov 9:22–41

    Article  Google Scholar 

  • Kale S, Arditi D (2006) Diffusion of ISO 9000 certification in the precast concrete industry. Constr Manage Econ 24:485–495

    Article  Google Scholar 

  • Leskovar VŽ, Premrov M (2011) An approach in architectural design of energy-efficient timber buildings with a focus on the optimal glazing size in the south-oriented façade. Energy Build 43:3410–3418

    Article  Google Scholar 

  • Li CZ, Hong J, Xue F, Shen GQ, Xu X, Mok MK (2016) Schedule risks in prefabrication housing production in Hong Kong: a social network analysis. J Cleaner Prod 134:482–494

    Google Scholar 

  • Lu W, Huang GQ, Li H (2011) Scenarios for applying RFID technology in construction project management. Autom Constr 20:101–106

    Article  Google Scholar 

  • Marasini R, Dawood NN, Hobbs B (2001) Stockyard layout planning in precast concrete products industry: a case study and proposed framework. Constr Manage Econ 19:365–377

    Article  Google Scholar 

  • Meadows DH, Goldsmith EI, Meadow P (1972) The limits to growth. Earth Island Limited London

    Google Scholar 

  • Meiling JH, Sandberg M, Johnsson H (2013) A study of a plan-do-check-act method used in less industrialized activities: two cases from industrialized housebuilding. Constr Manage Econ 1–17

    Google Scholar 

  • Nadim W, Goulding JS (2010) Offsite production in the UK: the way forward? A UK construction industry perspective. Constr Innov 10:181–202

    Article  Google Scholar 

  • Pan W, Dainty AR, Gibb AG (2012) Establishing and weighting decision criteria for building system selection in housing construction. J Constr Eng Manage 138:1239–1250

    Article  Google Scholar 

  • Pan W, Gibb AG, Dainty AR (2007) Perspectives of UK housebuilders on the use of offsite modern methods of construction. Constr Manage Econ 25:183–194

    Article  Google Scholar 

  • Peña-Mora F, Han S, Lee S, Park M (2008) Strategic-operational construction management: hybrid system dynamics and discrete event approach. J Constr Eng Manage 134:701–710

    Article  Google Scholar 

  • Polat G (2008) Factors affecting the use of precast concrete systems in the United States. J Constr Eng Manage 134:169–178

    Article  Google Scholar 

  • Shen Q, Chen Q, Tang B-S, Yeung S, Hu Y, Cheung G (2009) A system dynamics model for the sustainable land use planning and development. Habitat Int 33:15–25

    Article  Google Scholar 

  • Tam VW, Hao JJ (2014) Prefabrication as a mean of minimizing construction waste on site. Int J Constr Manage 14:113–121

    Google Scholar 

  • Tam VW, Tam C, Zeng S, Ng WC (2007) Towards adoption of prefabrication in construction. Build Environ 42:3642–3654

    Article  Google Scholar 

  • Tam VWY, Fung IWH, Sing MCP, Ogunlana SO (2015) Best practice of prefabrication implementation in the Hong Kong public and private sectors. J Clean Prod 109:216–231

    Article  Google Scholar 

  • Yin SY, Tserng HP, Wang J, Tsai S (2009) Developing a precast production management system using RFID technology. Autom Constr 18:677–691

    Article  Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to W. K. Huang .

Editor information

Editors and Affiliations

Rights and permissions

Reprints and permissions

Copyright information

© 2018 Springer Nature Singapore Pte Ltd.

About this paper

Check for updates. Verify currency and authenticity via CrossMark

Cite this paper

Huang, W.K., Xu, X.X., Chen, K., Wu, H.Y., Li, Z.D. (2018). Causal Loop Analysis on the Impact of Schedule Risks in Prefabrication Housing Production in Hong Kong. In: Chau, K., Chan, I., Lu, W., Webster, C. (eds) Proceedings of the 21st International Symposium on Advancement of Construction Management and Real Estate. Springer, Singapore. https://doi.org/10.1007/978-981-10-6190-5_38

Download citation

Publish with us

Policies and ethics