An Empirical Estimation of Settlement-Time Relationship Due to Shield Tunneling in Gravelly Soils

  • Conference paper
Proceedings of the 2nd International Symposium on Asia Urban GeoEngineering

Part of the book series: Springer Series in Geomechanics and Geoengineering ((SSGG))

  • 1912 Accesses

Abstract

This paper reported the surface settlement-time relationship due to shield tunneling in gravelly soils. Field data monitored during the construction of Taoyuan International Airport MRT, Hukou power-cable tunnels, and Beijing Metro Line 1 tunnels were collected and analyzed. Based on the field data, the hyperbolic model was proposed to simulate the settlement-time relationship above the centerline of the tunnel. Based on the field measurements, it was found that the settlement-time relationship due to shield tunnelling could be property approximated with the hyperbolic model. The hyperbolic constant 1/a represented the surface settlement that occurred during the first day after the face of shield passed the monitoring sensor. For shield tunnelling in gravelly soils, the mean of initial settlement speed was 2.5 mm/day. The constant 1/b represented the long-term ultimate settlement due to shield tunnelling. For tunnelling in gravelly soils, the measured maximum settlement was only 4.70 to 8.06 mm. These values were much lower than the long-term settlements due to shield tunnelling in clay, and clay-and-sand grounds. The reason for these extremely small settlements was most probably due to the high stiffness and strength of the gravelly soils.

This is a preview of subscription content, log in via an institution to check access.

Access this chapter

Chapter
USD 29.95
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
eBook
USD 129.00
Price excludes VAT (USA)
  • Available as EPUB and PDF
  • Read on any device
  • Instant download
  • Own it forever
Softcover Book
USD 169.99
Price excludes VAT (USA)
  • Compact, lightweight edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info
Hardcover Book
USD 169.99
Price excludes VAT (USA)
  • Durable hardcover edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info

Tax calculation will be finalised at checkout

Purchases are for personal use only

Institutional subscriptions

References

  • CECI Engineering Consultants Incorporation: Taiwan Taoyuan International Airport access MRT System-Construction Proposal for Lot CUO2A, Taipei, Taiwan (2009). (In Chinese)

    Google Scholar 

  • Chieh-Hsing Construction Co. and Shimizu Corporation Co.: Chu-Kung Extra High Voltage Substation Outlet kV Power-cable Turnkey Project: Shield Tunnel Construction Proposal, Taipei, Taiwan (2009). (In Chinese)

    Google Scholar 

  • Fang, Y.S., Lin, S.J., Lin, J.S.: Time and settlement in EPB shield tunnelling. Tunn. Tunn. 25, 26–27 (1993)

    Google Scholar 

  • Fujita, K.: Prediction of settlements by shield tunnelling. In: Proceedings, International Conference on Soil Mechanics, vol. 1, pp. 239–246 (1982)

    Google Scholar 

  • Hwang, R.N., Ju, D.H., Tsai, M.S., Fang, Y.S.: Soft ground tunnelling in Taiwan. In: Proceedings, US/Taiwan Geotechnical Engineering Collaboration Workshop, Taipei, pp. 77–90 (1995)

    Google Scholar 

  • Japan Society of Civil Engineers: Japan Standard for Shield Tunnelling, 3 edn. (1996). (in Japanese)

    Google Scholar 

  • Zhou, S., Wang, J.A.: The surface settlement analysis of curved tunnel shield. Chin. J. Undergr. Space Eng. 3(5), 909–913 (2007). (In Chinese)

    Google Scholar 

Download references

Acknowledgements

The authors wish to acknowledge the Bureau of High Speed Rail, CECI Engineering consultants, Inc., and RSEA Engineering Corporation/Okumura Corporation Joint Venture for providing valuable information and support. The financial assistance of the Ministry of Science and Technology (Grant No.: MOST 105-2221-E-009-021-MY3) is gratefully acknowledged.

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Yung-Show Fang .

Editor information

Editors and Affiliations

Rights and permissions

Reprints and permissions

Copyright information

© 2018 Springer Nature Singapore Pte Ltd. and Zhejiang University Press

About this paper

Cite this paper

Fang, YS., Kuo, LY., Lin, CM., Shih, YC. (2018). An Empirical Estimation of Settlement-Time Relationship Due to Shield Tunneling in Gravelly Soils. In: Chen, R., Zheng, G., Ou, C. (eds) Proceedings of the 2nd International Symposium on Asia Urban GeoEngineering. Springer Series in Geomechanics and Geoengineering. Springer, Singapore. https://doi.org/10.1007/978-981-10-6632-0_24

Download citation

  • DOI: https://doi.org/10.1007/978-981-10-6632-0_24

  • Publisher Name: Springer, Singapore

  • Print ISBN: 978-981-10-6631-3

  • Online ISBN: 978-981-10-6632-0

  • eBook Packages: EngineeringEngineering (R0)

Publish with us

Policies and ethics